Built by Kaizen, not a live government website
OST-27-74580

Zero-Emission Bus Fleet Transition Phase III (Segment 162)

City of Philadelphia · PA · LoNo · Federal Transit Administration

Merit ReviewOn track$5.1M requested
Requested

$5,100,000

Total project cost

$11,349,334

Federal share

60%

Submitted

Jan 25, 2026

Project description

The project addresses a documented deficiency on a corridor carrying 91,000 vehicles per day, 14 percent of which are trucks. Work includes design, construction, and post-construction monitoring. The applicant has completed preliminary engineering and holds committed non-federal match.

Applicant type: City

Project type: Bus electrification

State: PA

Congressional districts: PA-01

Assigned owner: Andre Boone

Source system: OST GNS

Prior applications by this applicant

Repeat submissions are the raw material for serial-resubmission detection.

No prior applications on file for City of Philadelphia.