Zero-Emission Bus Fleet Transition Phase II (Segment 167)

Metropolitan Atlanta Rapid Transit Authority · GA · LoNo · Federal Transit Administration

SubmittedBreached$122.5M requested
Requested

$122,500,000

Total project cost

$196,117,857

Federal share

80%

Submitted

Aug 5, 2026

Project description

This request funds construction of improvements identified in the region's adopted long-range transportation plan. The facility is currently rated in poor condition and carries a state-designated freight route. Delivery is scheduled across 27 construction seasons.

Applicant type: Transit Agency

Project type: Bus electrification

State: GA

Congressional districts: GA-07, GA-09, GA-03

Assigned owner: Robert Castleberry

Source system: OST GNS

Prior applications by this applicant

Repeat submissions are the raw material for serial-resubmission detection.

No prior applications on file for Metropolitan Atlanta Rapid Transit Authority.