GEMS-2027-636451
Rural Two-Lane Roadway Departure Countermeasures (Segment 136)
Delaware Department of Transportation · DE · SS4A · Federal Highway Administration
Requested
$193,900,000
Total project cost
$315,990,783
Federal share
70%
Submitted
Mar 3, 2026
Project description
The project addresses a documented deficiency on a corridor carrying 85,000 vehicles per day, 15 percent of which are trucks. Work includes design, construction, and post-construction monitoring. The applicant has completed preliminary engineering and holds committed non-federal match.
Applicant type: State DOT
Project type: Roadway safety
State: DE
Congressional districts: DE-AL
Assigned owner: Karen Braddock
Source system: GEMS
Prior applications by this applicant
Repeat submissions are the raw material for serial-resubmission detection.No prior applications on file for Delaware Department of Transportation.