GEMS-2027-390214
US-53 Truss Bridge Replacement
Connecticut Department of Transportation · CT · BIP · Federal Highway Administration
Requested
$140,900,000
Total project cost
$296,375,196
Federal share
60%
Submitted
Jul 18, 2026
Project description
Funds would support replacement of assets that have exceeded their useful life and are subject to escalating maintenance costs. The project was developed with local and regional partners and is consistent with the state's asset management plan.
Applicant type: State DOT
Project type: Bridge replacement
State: CT
Congressional districts: CT-01, CT-05, CT-02
Assigned owner: Jonathan Yamashita
Source system: GEMS
Prior applications by this applicant
Repeat submissions are the raw material for serial-resubmission detection.No prior applications on file for Connecticut Department of Transportation.