GEMS-2027-241288
High Injury Network Intersection Retrofit (Segment 49)
Nevada Department of Transportation · NV · INFRA · Office of the Secretary of Transportation
Requested
$85,000,000
Total project cost
$137,847,635
Federal share
80%
Submitted
Aug 4, 2026
Project description
The project addresses a documented deficiency on a corridor carrying 87,000 vehicles per day, 24 percent of which are trucks. Work includes design, construction, and post-construction monitoring. The applicant has completed preliminary engineering and holds committed non-federal match.
Applicant type: State DOT
Project type: Roadway safety
State: NV
Congressional districts: NV-01
Assigned owner: Thomas Ashby
Source system: GEMS
Prior applications by this applicant
Repeat submissions are the raw material for serial-resubmission detection.No prior applications on file for Nevada Department of Transportation.