GEMS-2027-011945
US-43 Truss Bridge Replacement
Illinois State Police · IL · BIP · Federal Highway Administration
Requested
$280,200,000
Total project cost
$413,535,097
Federal share
70%
Submitted
Mar 2, 2026
Project description
The applicant proposes to eliminate a persistent safety and reliability constraint serving 124,000 residents. The scope includes structural work, drainage, and multimodal accommodations. Environmental review is underway and no significant impacts are anticipated.
Applicant type: State Agency
Project type: Bridge replacement
State: IL
Congressional districts: IL-17, IL-07
Assigned owner: Karen Braddock
Source system: GEMS
Prior applications by this applicant
Repeat submissions are the raw material for serial-resubmission detection.No prior applications on file for Illinois State Police.