FRA-CRISI-27-671
Track Capacity Expansion at Interlocking 70
Nebraska Department of Transportation · NE · FSP-NEC · Federal Railroad Administration
Requested
$116,000,000
Total project cost
$246,574,999
Federal share
60%
Submitted
May 17, 2026
Project description
The project addresses a documented deficiency on a corridor carrying 45,000 vehicles per day, 14 percent of which are trucks. Work includes design, construction, and post-construction monitoring. The applicant has completed preliminary engineering and holds committed non-federal match.
Applicant type: State DOT
Project type: Intercity passenger rail
State: NE
Congressional districts: NE-03, NE-01
Assigned owner: Robert Castleberry
Source system: FRA Grant Solutions
Prior applications by this applicant
Repeat submissions are the raw material for serial-resubmission detection.No prior applications on file for Nebraska Department of Transportation.